Segment One Construction Schedule

March 15th - Stage 1

March 28th - Stage 2

Mid-Summer - Stage 3

October/November - Stage 4

Mid-December - Roadway open, but work not complete

Spring 2005 - Pavement marking and landscaping

  Last Updated 03/25/05