Segment Two Construction Schedule

March 6th - Stage 1

April - Stage 2

May - South First Street

June - North First Street

Mid-July - Stage 3

Mid-August - Stage 4

November - Stage 5

Mid-December - Roadway open, but work not complete

Spring 2007 - Pavement marking and landscaping

East Washington Avenue Segment 2 Timeline

  Last Updated 03/31/06