Segment Three Construction Schedule
Stage 1 (March 12th
- End of March)
East Washington Avenue - construct temporary pavement, temporary
signals, sanitary sewer crossing at Johnson Street, and construct water
main crossing at McCormick Avenue
Stage 2 (April
- Mid June)
East
Washington Avenue - construction
of outbound lanes and half of Starkweather Creek Bridge
Starkweather Creek Bike Path - work
on south half between Darbo Drive and East Washington Avenue
Stage 2A (Mid June - Late June)
East
Washington Avenue - construction
of outbound lanes
Starkweather Creek Bike Path - work
on south half between Darbo Drive and East Washington Avenue
Stage 3 (Late June)
East
Washington Avenue - median
construction
Stage 3A (July)
East
Washington Avenue - median
construction and construction of inbound lanes
Stage 4 (Early
August - Mid August)
East
Washington Avenue - construction
of inbound lanes
Starkweather Creek Bike Path - work
on north half between East Washington Avenue and Commercial Avenue
Stage 4A (September - October)
East
Washington Avenue - finish
inbound lanes and inbound half of Starkweather Creek Bridge
Starkweather Creek Bike Path -
finish work on north half between East Washington Avenue and Commercial
Avenue
Stage 5 (November)
East
Washington Avenue - median
construction (Fifth Street to McCormick Avenue)
Starkweather Creek Bike Path - erect
prefabricated steel truss across East Washington Avenue
Roadway anticipated to be
opened early December, but work not completed
Stage 6 (Spring 2008)
Median streetscaping; plant
trees, shrubs and perennials; install final pavement marking |