Segment Four Construction Schedule

Stage 1A (Mid January - March)
East Washington Avenue
- construct temporary bridge widening for inbound East Washington Avenue over HWY 30, widen box culvert on Aberg Avenue over Starkweather Creek

Stage 1B (March)
East Washington Avenue - construct temporary pavement crossovers for future stages and construction of storm sewer across southbound lane of HWY 30

HWY 30/Aberg Avenue - construct temporary pavement crossovers for future stages and storm sewer work

Fair Oaks Avenue - construct temporary pavement and temporary concrete barrier to protect bridge piers

Ramps - construct temporary pavement for future stages and storm sewer

Stage 2 (End of March - Mid June)
East Washington Avenue - construct northbound lanes and bridge over HWY 30 and Rethke Avenue construction

HWY30/Aberg Avenue - construct westbound lanes, retaining walls, and McCormick Avenue cul-de-sac

Fair Oaks Avenue - construct northbound lanes

Frontage Roads - construct Commercial Avenue, north of HWY 30 and construct Commercial Avenue, south of HWY 30

Stage 3A (Mid June - End June)
East Washington Avenue - construct utilities across median and place temporary pavement crossovers for next stage

HWY 30/Aberg Avenue - place temporary pavement crossovers for next stage

Fair Oaks Avenue - construct southbound lanes

Frontage Roads - construct Commercial Avenue near Rethke Avenue

Stage 3B (End June - Mid July)
East Washington Avenue - work on new bridge over HWY 30

HWY 30/Aberg Avenue - place temporary pavement crossovers for next stage

Fair Oaks Avenue - construct southbound lanes

Frontage Roads - construct Commercial Avenue near Rethke Avenue

Stage 4 (Mid July - End October)
East Washington Avenue - construct southbound lanes and bridge over HWY 30, construct McCormick Avenue and Melvin Court

HWY 30/Aberg Avenue - construct eastbound lanes

Frontage Roads - construct Commercial Avenue at intersections of Christianson Avenue and Gannon Avenue

Stage 5 (End October - December 1)
East Washington Avenue - construct medians, left turn lanes, and permanent signals

HWY 30/Aberg Avenue - construct medians and shoulders

Stage 6 (Spring 2010)
Median streetscaping; plant trees, shrubs and perennials; install final pavement marking

  Last Updated 02/04/09