|
Segment One Traffic
Control Plan
Major construction
operations are anticipated to be completed in mid-December 2004 with
pavement marking and median landscaping being completed in Spring 2005.
East Washington Avenue will remain open to traffic during the project with
two lanes in each direction. Cross-traffic and left turns will be limited
to the signalized intersections of Paterson, Ingersoll and Baldwin
Streets with other non-signalized intersections restricted to
right-in/right-out access. Intersections may be periodically closed for
short periods of time as required to allow for utility installations and
concrete paving operations. Parking will not be allowed along the avenue
during construction.
In
order to reconstruct East Washington Avenue while maintaining traffic,
construction operations will be completed in four stages:
Stage 1 (mid-March to early-April) will involve
closure of the median lanes to allow for the removal of the median and
temporary pavement widening in the median along the inbound lanes in
preparation for Stage 2.
Stage 2 (early-April to July) will consist of
four lanes of bi-directional traffic (two lanes in each direction) on the
existing inbound lanes while the outbound lanes are reconstructed.
Stage 3 (August to October) will switch the four
lanes of traffic over to the newly constructed outbound lanes while the
inbound lanes are reconstructed.
Stage 4 (November) will return to divided
traffic with two lanes in each direction in the right and center driving
lanes for completion of the median and left-turn lanes as well as
bump-outs. An exhibit
further detailing the construction staging is on display.
Temporary pedestrian crossings of East Washington Avenue will be provided
at the signalized intersections of Patterson, Ingersoll, and Baldwin
Streets. Bus stops will be reduced to three pairs of stops within
the construction area at the signalized intersections with accessible
boarding areas in the
median during Stage 2 and
Stage 3 of construction.
For more information visit Metro Transit at:
http://www.mymetrobus.com/2003/Detours/EastWashConstruction.htm
Access at most intersections as well as to residential and business
driveways will be maintained as much as possible. During
reconstruction of the intersections and traveled lanes, local and
cross-traffic may be driving on graveled surfaces before paving
operations. A paving gap will be left at business driveways that
have no alternate access, allowing traffic to enter and exit. If
approved by the business, the construction contractor will also have the
option of paving the roadway in front of the driveway using a quick curing
concrete. Paving with quick curing concrete requires a 24 to 36 hour
closure of the driveway but results in a smoother pavement in front of the
driveway and less overall inconvenience. Businesses are encouraged
to work closely with the construction contractor and project manager
during construction to discuss business access and work out acceptable
solutions for everyone.
For a diagram
of the staging, open this link:
Staging Diagram
To
keep the public informed and provide an open line of communication, the
construction contractor and project manager will hold regular meetings
with local businesses and property owners to discuss the project schedule,
vehicular access, pedestrian access, and other construction issues.
Meeting times will be announced on the
Meetings Page.
The
City of Madison has agreed to implement a construction traffic-management
plan, which includes many measures to minimize traffic diversion to the
residential neighborhoods and to minimize the impacts of accessibility.
Measures include maximizing signal green-time, providing left-turn lanes,
installing dynamic message signs, and the use of an outreach program to
inform motorists. The plan also includes keeping access open to local
businesses, providing pedestrian crossings, and encouraging the use of
transit services.
|