|
Segment Three Traffic
Control PlanMajor construction
operations are anticipated to start around March 12th and be
completed in mid-December 2007 with pavement marking and median
landscaping being completed in Spring 2008. East Washington Avenue
will remain open to traffic during the project with two lanes in each
direction. Cross-traffic and left turns will be limited to the
signalized intersection of Fourth Street, Milwaukee/North Street, Johnson
Street, and Marquette Street. Other non-signalized
intersections will be restricted to right-in/right-out access, or closed.
Intersections may be periodically closed for short periods of time as
required to allow for utility installations and concrete paving
operations.
This segment also includes the construction of the Starkweather Creek
Bike Path from Darbo Drive to Commercial Avenue. A new pedestrian
bridge over East Washington Avenue will be added, including stream bank
improvements and landscaping enhancements.
In order to reconstruct East Washington Avenue while maintaining
traffic, construction operations will be completed in five major stages:
Stage 1 (March) will involve closure of the
median lanes to allow for the removal of the median and temporary pavement
widening. A temporary Milwaukee Street bypass will be constructed
and a sanitary sewer crossing at Johnson Street. The crossovers will
also be constructed and temporary signals will be installed in preparation
for
Stage 2.
Stage 2 (April to June) will consist of
four lanes of bi-directional traffic (two lanes in each direction) on the
existing inbound lanes while the outbound lanes are reconstructed.
Work will occur on the south half of the new Starkweather Creek Bridge,
Starkweather Creek Bike Path, and stream bank work.
Stage 3 (July) will involve closure of
the median lanes to construct utilities across the median. Temporary
pavement and temporary signs will be installed in preparation for
Stage 4.
Stage 4 (August to October) will consist of four
lanes of bi-directional traffic (two lanes in each direction) on the newly
constructed outbound lanes while the inbound lanes are reconstructed.
Work will occur on the north half of the new Starkweather Creek Bridge and
Starkweather Creek Bike Path.
Stage 5 (November) will return to divided
traffic with two lanes in each direction in the right and center driving
lanes for completion of the median and left-turn lanes. Landscape
plantings in the median will carry over into the spring of 2008.
Spring
2008 the median streetscaping will be
constructed. The permanent pavement markings will be installed.
Temporary pedestrian crossings will be provided
crossing East Washington Avenue at the following intersections:
Fourth Street, Milwaukee/North Street, Johnson Street, and Marquette
Street. Bus stops will
be maintained as much as possible throughout the construction staging. For more information visit Metro Transit at:
http://www.mymetrobus.com
Access at most intersections as well as to residential and business
driveways will be maintained as much as possible. During
reconstruction of the intersections and traveled lanes, local and
cross-traffic may be driving on graveled surfaces before paving
operations. A paving gap will be left at business driveways that
have no alternate access, allowing traffic to enter and exit. If
approved by the business, the construction contractor will also have the
option of paving the roadway in front of the driveway using a quick curing
concrete. Paving with quick curing concrete requires a 24 to 36 hour
closure of the driveway but results in a smoother pavement in front of the
driveway and less overall inconvenience. Businesses are encouraged
to work closely with the construction contractor and project manager
during construction to discuss business access and work out acceptable
solutions for everyone.
To
keep the public informed and provide an open line of communication, the
construction contractor and project manager will hold regular meetings
with local businesses and property owners to discuss the project schedule,
vehicular access, pedestrian access, and other construction issues.
Meeting times will be announced on the
Meetings Page.
The
City of Madison has agreed to implement a construction traffic-management
plan, which includes many measures to minimize traffic diversion to the
residential neighborhoods and to minimize the impacts of accessibility.
Measures include maximizing signal green-time, providing left-turn lanes,
installing dynamic message signs, and the use of an outreach program to
inform motorists. The plan also includes keeping access open to local
businesses, providing pedestrian crossings, and encouraging the use of
transit services.
|